Checking a customer change request from the minutes against the plan
- Starting point
- A special machine builder is constructing a linked production line. In the acceptance meeting the customer asks for a different workpiece holder. The design lead finds the minutes and the old specification in the documents, but does not know what the change means for assembly and factory acceptance.
- How Linetrack is used
- The design lead asks amber for the wording of the change request and, in the same chat, for the plan status of the line: when is the design release due, which assembly tasks depend on it, how busy is design? Linetrack answers only the specific question, and everyone sees only projects they can also open in Linetrack.
- Result
- The follow-up question to the project manager and the search through several lists are no longer needed. The design lead goes into the conversation with the customer with a reliable schedule and decides whether the change fits the plan or the factory acceptance must move.